N Conway Hampton Inn & Suites
Thursday, December 22, 2005
2005 12 20 Glycol Heating the Slab
Thursday, December 08, 2005
2005 12 07 Cold Sets In
Many more forms on the east side of the hotel.
Light pole bases and versalock wall stored on site.
Electrical Xfrmr moved to south side of waterpark structure.
Saturday, December 03, 2005
2005 12 01 Asphalt on Upper Lot
- Lots of asphalt on the upper lot
- Foundation wall work continues
Thursday, November 10, 2005
2005 11 09 Concrete Footings
Pouring Concrete Footings!
Wednesday, November 02, 2005
2005 11 02 Additional Sitework
The sign is visible from the street.
This picture shows the DOT drain line which will need to be moved to avoid the hotel structure.
Drainage catch basins are being installed.
Notice the existing house structure is completely removed.
The last picture is the subcontractor's equipment and materials on-site. Anticipate pouring concrete footings next week.
Saturday, October 29, 2005
2005 10 26 Sitework Progress
These pix show the extent that sitework has progressed on the Conway site.
The structures have been torn down and most of the topsoil has been moved and graded.